Harris 7/14/16

The exterior of your home is really coming along. The dumpsters, trailers and miscellaneous materials have been moved off-site. The irrigation system is operational, and O’Brien and his crew have been fine-tuning it. The trees and shrubs have been planted, the willows on the south side of the ditch were removed earlier this week, and he plans to hydroseed and lay sod tomorrow. The exterior grill area is almost complete, with the countertop, tile, and grout finished up. The painters continue to make progress on the final wall coat, and mirrors were installed in the bathrooms on Monday. Doors are being re-hung, and hardware is being installed. The electrician has fixtures and plates installed in the rooms that have been painted, and continues his trim out where he can. JJs Appliance is on site today working on appliance install in conjunction with the electrician.